How long does it take to finish a basement? Utah timelines and steps

Utah basement companies that post a timeline say a typical finish takes 4 to 12 weeks of construction, and 6 to 8 weeks is the most common answer (13 companies, Nov 23, 2026). Add time before that for design, quotes and permit review, and more for bathrooms, kitchens or egress windows.
- Permit review happens before construction starts; ask your city for current review times.
- Inspections set the pace: rough-in must pass before insulation and drywall.
- Bathrooms, kitchens, new egress windows and custom built-ins add time.
What Utah companies say
Here is what basement companies in this directory publish on their own websites:
| Company | Posted typical timeline |
|---|---|
| Almost Anything Remodeling | 6 to 12 weeks, planning to completion |
| Kind Build Co. | about 6 to 8 weeks, framing to final walkthrough |
| Valley Brothers | 4 to 8 weeks |
| Apex Construction Utah | about 10 to 12 weeks once construction begins |
| Soul Builders SLC | 4 to 8 weeks, design to completion |
| Baker Kitchen & Bath | 6 to 12 weeks |
| South Valley Building Co. | 4 to 8 weeks |
| Salt Lake City Contractors | 6 to 8 weeks for most standard finishes |
| Creative Construction Solutions | 6 to 10 weeks |
| RemodelCo - Basements, Kitchens & Baths - Salt Lake City | about 6 to 8 weeks of active construction |
| Rock Top Construction | 4 to 8 weeks |
| CHERRYWOOD CONSTRUCTION INC. | 6 to 12 weeks, permit approval to completion |
| Affordable Basement Pros | about 10 to 12 weeks |
The steps, in order
- Plan and test. Decide on rooms, get design help if you need it, test for radon and fix any moisture.
- Get quotes and sign a contract. Compare written quotes for the same plan and check the contractor's license.
- Permit. Submit plans to your city and wait for approval.
- Framing and egress. Frame walls and soffits; cut and install any new egress windows and wells.
- Rough-in. Electrical, plumbing, HVAC and gas, then the rough-in inspection.
- Insulation. Insulate exterior walls (inspected in some cities).
- Drywall. Hang, tape, mud and texture.
- Finishes. Paint, doors and trim, flooring, cabinets, fixtures and lighting.
- Final inspection. The city signs off and the space is legally finished.
What slows a basement down
- Permit review times and corrections to plans.
- Failed inspections that need rework.
- Water, radon or structural surprises found once work starts.
- Special-order items like windows, cabinets or tile.
- Changes you make mid-project.
Browse basement specialists or pick a city: Salt Lake City, Sandy, West Jordan, Lehi, Orem, Kaysville, Bountiful, Roy.
Questions people ask
How long does it take to finish a basement?
Utah basement companies that post timelines say 4 to 12 weeks of construction, most often 6 to 8 weeks, plus time for design and permit review before work starts.
What is the first step in finishing a basement?
Plan the rooms, test for radon and fix any moisture problems, then get quotes and a permit before framing.
How many inspections does a basement finish need?
Typically a rough-in inspection (framing, electrical, plumbing and mechanical) before walls are covered, sometimes an insulation inspection, and a final inspection.
Can I live in my house while the basement is finished?
Usually yes. Ask your contractor about dust control, noise and when utilities might be shut off.
Sources
- Each company's own website (linked from its listing page)
- West Jordan: Basement finish permit details
- Utah DEQ: Radon Program
General information, not legal, engineering or financial advice. Codes, fees and city rules change; confirm with your city or county building department and the official sources above before you sign or build. Company prices and timelines are what each company posted on its own website when we checked (Nov 23, 2026); they are not quotes.