Home › Guides › How long it takes

How long does it take to finish a basement? Utah timelines and steps

Last updated · By the Utah Basement Finishers team · Sources at the bottom

Unfinished basement with block walls and open floor joists
Stock photo, not a listed company's work.
At a glance

Utah basement companies that post a timeline say a typical finish takes 4 to 12 weeks of construction, and 6 to 8 weeks is the most common answer (13 companies, Nov 23, 2026). Add time before that for design, quotes and permit review, and more for bathrooms, kitchens or egress windows.

  • Permit review happens before construction starts; ask your city for current review times.
  • Inspections set the pace: rough-in must pass before insulation and drywall.
  • Bathrooms, kitchens, new egress windows and custom built-ins add time.

What Utah companies say

Here is what basement companies in this directory publish on their own websites:

CompanyPosted typical timeline
Almost Anything Remodeling6 to 12 weeks, planning to completion
Kind Build Co.about 6 to 8 weeks, framing to final walkthrough
Valley Brothers4 to 8 weeks
Apex Construction Utahabout 10 to 12 weeks once construction begins
Soul Builders SLC4 to 8 weeks, design to completion
Baker Kitchen & Bath6 to 12 weeks
South Valley Building Co.4 to 8 weeks
Salt Lake City Contractors6 to 8 weeks for most standard finishes
Creative Construction Solutions6 to 10 weeks
RemodelCo - Basements, Kitchens & Baths - Salt Lake Cityabout 6 to 8 weeks of active construction
Rock Top Construction4 to 8 weeks
CHERRYWOOD CONSTRUCTION INC.6 to 12 weeks, permit approval to completion
Affordable Basement Prosabout 10 to 12 weeks

Some count from design or permit approval, others from the start of framing, so compare carefully.

The steps, in order

  1. Plan and test. Decide on rooms, get design help if you need it, test for radon and fix any moisture.
  2. Get quotes and sign a contract. Compare written quotes for the same plan and check the contractor's license.
  3. Permit. Submit plans to your city and wait for approval.
  4. Framing and egress. Frame walls and soffits; cut and install any new egress windows and wells.
  5. Rough-in. Electrical, plumbing, HVAC and gas, then the rough-in inspection.
  6. Insulation. Insulate exterior walls (inspected in some cities).
  7. Drywall. Hang, tape, mud and texture.
  8. Finishes. Paint, doors and trim, flooring, cabinets, fixtures and lighting.
  9. Final inspection. The city signs off and the space is legally finished.

What slows a basement down

  • Permit review times and corrections to plans.
  • Failed inspections that need rework.
  • Water, radon or structural surprises found once work starts.
  • Special-order items like windows, cabinets or tile.
  • Changes you make mid-project.

Questions people ask

How long does it take to finish a basement?

Utah basement companies that post timelines say 4 to 12 weeks of construction, most often 6 to 8 weeks, plus time for design and permit review before work starts.

What is the first step in finishing a basement?

Plan the rooms, test for radon and fix any moisture problems, then get quotes and a permit before framing.

How many inspections does a basement finish need?

Typically a rough-in inspection (framing, electrical, plumbing and mechanical) before walls are covered, sometimes an insulation inspection, and a final inspection.

Can I live in my house while the basement is finished?

Usually yes. Ask your contractor about dust control, noise and when utilities might be shut off.

Sources

  1. Each company's own website (linked from its listing page) (timelines read Nov 23, 2026)
  2. West Jordan: Basement finish permit details
  3. Utah DEQ: Radon Program

General information, not legal, engineering or financial advice. Codes, fees and city rules change; confirm with your city or county building department and the official sources above before you sign or build. Company prices and timelines are what each company posted on its own website when we checked (Nov 23, 2026); they are not quotes.